Due to heavy soil transportation to the 5th and 6th holes the front nine will be closed according to the following schedule:
- Monday 10th January – Site mobilization
- Tuesday 11th January – Commence removal/relocation of contaminated fill (approx. 2 days)
- Thursday 13th January – Commence capping/remediation of contaminated fill (approx. 2 days)
- Monday 17th January – Contingency day
- Tuesday 18th January – Back to normal working conditions
At this stage Tuesday 11th, Thursday 13th and Friday 14th competitions will be cancelled
Social 9 hole rounds can still be booked on the website as usual
Bluefit are looking into running their own 9 hole competitions but that is not confirmed at this stage
Match Committee